Assignment as site manager on the contractor side of Citybanan.
Strukton Rail
Assignment as site manager on the contractor side in the Citybanan project for the BEST-contract in the six-kilometer track tunnel with double trains between Södra station and Tomteboda. At the final stage, OMT AB has been assigned the responsibility for completion of the project. The project started 2014 and includes construction of track, wire connection, signal systems, telecommunications technology and installation of fire alarms. The construction was completed in 2016 and is expected to an amount of approximately 270 million SEK.
Contacts
Business management Board of directors
John Filipiak Wallderin
President, Chairman of the Board and Owner of OMT
+4670-511 01 67
john@omtab.se